121) Control procurements belongs to:
a) Initiating process group
b) Executing process group
c) Controlling process group
d) Monitoring and controlling process group
122) Which of these is a reason to start a project:
a) Problem
b) Market
c) Opportunity
d) All of the above
123) Which of the following is true about project charter:
a) When the project charter is approved, the project becomes officially authorized
b) Provides the project manager with the authority to apply organizational
resources to project activities
c) It is a direct way for senior management to formally accept and commit to the project
d) All of the above
124) The project charter contains:
a) Business needs
b) Risks
c) Quality plan
d) None of the above
125) Scope baseline includes:
a) WBS
b) WBS dictionary
c) Project scope statement
d) All of the above
126) Which of the following is true about project closure:
a) Contract closure is for each contract
b) Contract closure includes product verification and administrative closure
c) Administrative closure happens to close the project or each phase
d) All of the above
127) Administrative closure:
a) Happens once to close the project or each project phase
b) Needed to confirm that all deliverables have been provided
c) Ensures that official acceptance document has been obtained
d) All of the above
128) Which of the below are project selection methods:
a) Cost-benefit analysis
b) Payback period
c) Net present value
d) All of the above
129) WBS:
a) Prevents work from slipping through the cracks
b) Is the basis for estimates
c) Provides the team with an understanding of where their pieces fit in the project plan
d) All of the above
130) Principal sources of project failure:
a) Poorly identified customer needs
b) Poor planning
c) Poor control
d) All of the above
131) Change requests are created because of:
a) An omission in defining product/project scope
b) A value-adding change
c) An external event
d) All of the above
132) Which of the following is an example of a group creativity technique:
a) Brainstorming
b) Risk identification
c) Stakeholder creative communication
d) Powerpoint presentations
133) WBS includes all project work. Which of the following is also true about WBS?
a) It doesn't include product work
b) It does not include PM work
c) Total of work at lowest levels need not always roll up to higher levels as some extra work may be completed
d) None of the above
134) Critical chain method and critical path method are tools and techniques used in which of the below?
a) Estimate activity resources
b) Control schedule
c) Develop schedule
d) Estimate activity durations
135) Resource leveling is a tool/technique used in which of the below?
a) Develop schedule
b) Control schedule
c) Both a and b
d) Neither a nor b
136) Project Time Management is a process needed to:
a) Ensure timely completion of project
b) Track time taken for each activity
c) Bill the client for each hour of work done
d) None of the above
137) The outputs of 'Define Activities' are:
a) Activity list
b) Activity attributes
c) Milestone list
d) All of the above
138) Arrow diagramming method does not use:
a) Float
b) Finish to start relationship
c) Lag
d) Activities
139) Which of the following is discretionary dependency known as:
a) Preferential logic
b) Soft logic
c) Preferred logic
d) All of the above
140) Lead allows _____ of successor activity:
a) Acceleration
b) Deceleration
c) Tracking
d) Regression
a) Initiating process group
b) Executing process group
c) Controlling process group
d) Monitoring and controlling process group
122) Which of these is a reason to start a project:
a) Problem
b) Market
c) Opportunity
d) All of the above
123) Which of the following is true about project charter:
a) When the project charter is approved, the project becomes officially authorized
b) Provides the project manager with the authority to apply organizational
resources to project activities
c) It is a direct way for senior management to formally accept and commit to the project
d) All of the above
124) The project charter contains:
a) Business needs
b) Risks
c) Quality plan
d) None of the above
125) Scope baseline includes:
a) WBS
b) WBS dictionary
c) Project scope statement
d) All of the above
126) Which of the following is true about project closure:
a) Contract closure is for each contract
b) Contract closure includes product verification and administrative closure
c) Administrative closure happens to close the project or each phase
d) All of the above
127) Administrative closure:
a) Happens once to close the project or each project phase
b) Needed to confirm that all deliverables have been provided
c) Ensures that official acceptance document has been obtained
d) All of the above
128) Which of the below are project selection methods:
a) Cost-benefit analysis
b) Payback period
c) Net present value
d) All of the above
129) WBS:
a) Prevents work from slipping through the cracks
b) Is the basis for estimates
c) Provides the team with an understanding of where their pieces fit in the project plan
d) All of the above
130) Principal sources of project failure:
a) Poorly identified customer needs
b) Poor planning
c) Poor control
d) All of the above
131) Change requests are created because of:
a) An omission in defining product/project scope
b) A value-adding change
c) An external event
d) All of the above
132) Which of the following is an example of a group creativity technique:
a) Brainstorming
b) Risk identification
c) Stakeholder creative communication
d) Powerpoint presentations
133) WBS includes all project work. Which of the following is also true about WBS?
a) It doesn't include product work
b) It does not include PM work
c) Total of work at lowest levels need not always roll up to higher levels as some extra work may be completed
d) None of the above
134) Critical chain method and critical path method are tools and techniques used in which of the below?
a) Estimate activity resources
b) Control schedule
c) Develop schedule
d) Estimate activity durations
135) Resource leveling is a tool/technique used in which of the below?
a) Develop schedule
b) Control schedule
c) Both a and b
d) Neither a nor b
136) Project Time Management is a process needed to:
a) Ensure timely completion of project
b) Track time taken for each activity
c) Bill the client for each hour of work done
d) None of the above
137) The outputs of 'Define Activities' are:
a) Activity list
b) Activity attributes
c) Milestone list
d) All of the above
138) Arrow diagramming method does not use:
a) Float
b) Finish to start relationship
c) Lag
d) Activities
139) Which of the following is discretionary dependency known as:
a) Preferential logic
b) Soft logic
c) Preferred logic
d) All of the above
140) Lead allows _____ of successor activity:
a) Acceleration
b) Deceleration
c) Tracking
d) Regression